Greystones Marina Wicklow

Greystones Marina Wicklow

Greystones Marina Wicklow

Client : Wicklow County Council

Value : €50m

The civil and marine part of the Greystones Harbour and North Beach PPP project is approaching completion. This part of the project is being delivered by a joint venture between John Sisk & Son and Lagan Construction for the PPP Company Sispar which in turn is a joint venture between John Sisk & Son and Park Developments.

The civil & marine package is valued at around €50m and comprises approximately 80,000 m3 of dredging, 200,000 m3 of reclamation, 180,000t of rock armour up to 10t individual weight, 250,000t of rockfill, 54,000t of beach shingle, 115,000 m3 of concrete and 2500 linear metres of driven steel piles.

The project involves most aspects of marine civil engineering including dredging, reclamation, beach nourishment, rock armour, concrete armour, marine piling, underwater stone screeding, extensive

diving operations, seawalls, coastal revetments, breakwaters and slipways all of which are designed to function at all states of the tide. The breakwaters are designed for a 1 in 2000 year storm event

The construction process is complicated by the planning requirement to maintain availability of existing harbour facilities to local clubs and the general public throughout the construction period.

Part of the project contains the remains of an old disused Wicklow County Council landfill. Significant project works include landfill remediation involving the removal of approx. 9,000m3 of existing landfill material and sealing of the landfill cell using a bespoke geo-synthetic lining system and spreading of cell capping material and landscaping and seeding to form part of a public park. Further works include coastal protection works to eliminate future coastal erosion along the boundary of the old dump location.